Assessment Year | 2014 |
---|---|
Principal Product | Furniture |
NAICS | 337124: Metal Household Furniture Manufacturing |
SIC | 2514: Metal Household Furniture |
Sales Range | $1 M to 5M |
# of Employees | 240 |
Plant Area |
200,645
ft2
|
Annual Production | 106,000
pieces
|
Production Hrs. Annual | 2,168
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,346 | 1,161,152 |
kWh
|
$0.074 |
Electricity Demand | $88,061 | 4,622 |
kW-mo/yr
|
$19.05 |
Electricity Fees | $9,797 | - |
|
- |
Natural Gas | $67,781 | 10,750 |
MMBtu
|
$6.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,746 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,638 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $18,026 | $61,400 |
$14,092
189,408
kWh
|
$3,934
-
kW-mo/yr
|
- | |
02 | 2.2511: Insulate bare equipment | $7,108 | $21,254 | - | - |
$7,108
-
MMBtu
|
|
03 | 2.2414: Use waste heat from hot flue gases to preheat | $5,486 | $2,845 | - | - |
$5,486
-
MMBtu
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,633 | $2,600 |
$2,633
35,390
kWh
|
- | - | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,563 | $3,243 |
$(-395.0)
(-5,306)
kWh
|
$(-512.0)
-
kW-mo/yr
|
$2,470
-
MMBtu
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,147 | $500 |
$670
8,997
kWh
|
$477
-
kW-mo/yr
|
- | |
07 | 2.3132: Recharge batteries on during off-peak demand periods | $783 | $500 | - |
$783
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $36,746 | $92,342 |
$17,000
228,489
kWh
|
$4,682
-
kW-mo/yr
|
$15,064
-
MMBtu
|
||
TOTAL IMPLEMENTED | $29,638 | $71,088 |
$17,000
228,489
kWh
|
$4,682
-
kW-mo/yr
|
$7,956
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs