Assessment Year | 2013 |
---|---|
Principal Product | paint, printed products |
NAICS | 325510: Paint and Coating Manufacturing |
SIC | 2893: Printing Ink |
Sales Range | $10 M to 50M |
# of Employees | 93 |
Plant Area |
100,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 3,380
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,340 | 708,046 |
kWh
|
$0.077 |
Electricity Demand | $51,605 | 3,078 |
kW-mo/yr
|
$16.77 |
Natural Gas | $21,450 | 3,226 |
MMBtu
|
$6.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,413 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,263 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,922 | $17,910 |
$3,752
48,915
kWh
|
$2,170
-
kW-mo/yr
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $2,803 | $9,900 |
$1,669
21,769
kWh
|
$1,134
-
kW-mo/yr
|
- | |
03 | 2.2511: Insulate bare equipment | $2,635 | $4,905 | - | - |
$2,635
-
MMBtu
|
|
04 | 2.7134: Use photocell controls | $2,407 | $4,140 |
$1,522
19,845
kWh
|
$885
-
kW-mo/yr
|
- | |
05 | 2.4226: Use / purchase optimum sized compressor | $2,263 | $200 |
$1,274
16,607
kWh
|
$989
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,737 | $5,300 |
$1,737
22,653
kWh
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $646 | $300 |
$646
8,418
kWh
|
- | - | |
TOTAL RECOMMENDED | $18,413 | $42,655 |
$10,600
138,207
kWh
|
$5,178
-
kW-mo/yr
|
$2,635
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,263 | $200 |
$1,274
16,607
kWh
|
$989
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs