Assessment Year | 2012 |
---|---|
Principal Product | Treated Water |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 13 |
Plant Area |
2,560,000
ft2
|
Annual Production | 11,500
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,045,469 | 11,979,368 |
kWh
|
$0.087 |
Electricity Demand | $388,588 | 25,575 |
kW-mo/yr
|
$15.19 |
Electricity Fees | $11,590 | - |
|
- |
Natural Gas | $257,486 | 46,277 |
MMBtu
|
$5.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $187,969 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $177,897 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1336: Install equipment to utilize waste fuel | $48,619 | $2,000 | - | - |
$48,619
-
MMBtu
|
- | |
02 | 2.4226: Use / purchase optimum sized compressor | $24,957 | $15,925 |
$19,170
219,585
kWh
|
$5,787
-
kW-mo/yr
|
- | - | |
03 | 3.1191: Change procedures / equipment / operating conditions | $10,072 | $18,680 |
$8,128
93,104
kWh
|
$1,944
-
kW-mo/yr
|
- | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $2,223 | $4,200 | - | - |
$2,223
-
MMBtu
|
- | |
05 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $102,098 | $275,000 |
$65,475
750,000
kWh
|
$15,190
-
kW-mo/yr
|
$28,933
-
MMBtu
|
$(-7,500.0) | |
TOTAL RECOMMENDED | $187,969 | $315,805 |
$92,773
1,062,689
kWh
|
$22,922
-
kW-mo/yr
|
$79,775
-
MMBtu
|
$(-7,500.0) | ||
TOTAL IMPLEMENTED | $177,897 | $297,125 |
$84,645
969,585
kWh
|
$20,977
-
kW-mo/yr
|
$79,775
-
MMBtu
|
$(-7,500.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs