ITAC Assessment: SD0452
ITAC logo
ITAC Assessment: SD0452
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Treated Water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4952: Sewerage Systems
Sales Range $10
M
to 50
M
# of Employees 13
Plant Area 2,560,000
ft2
Annual Production 11,500
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,045,469 11,979,368
kWh
Electricity Demand $388,588 25,575
kW-mo/yr
Electricity Fees $11,590 -
Natural Gas $257,486 46,277
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $187,969 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $177,897

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.1336: Install equipment to utilize waste fuel $48,619 $2,000 - - $48,619
-
MMBtu
-
02 2.4226: Use / purchase optimum sized compressor $24,957 $15,925 $19,170
219,585
kWh
$5,787
-
kW-mo/yr
- -
03 3.1191: Change procedures / equipment / operating conditions $10,072 $18,680 $8,128
93,104
kWh
$1,944
-
kW-mo/yr
- -
04 2.2414: Use waste heat from hot flue gases to preheat $2,223 $4,200 - - $2,223
-
MMBtu
-
05 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $102,098 $275,000 $65,475
750,000
kWh
$15,190
-
kW-mo/yr
$28,933
-
MMBtu
$(-7,500.0)
TOTAL RECOMMENDED $187,969 $315,805 $92,773
1,062,689
kWh
$22,922
-
kW-mo/yr
$79,775
-
MMBtu
$(-7,500.0)
TOTAL IMPLEMENTED $177,897 $297,125 $84,645
969,585
kWh
$20,977
-
kW-mo/yr
$79,775
-
MMBtu
$(-7,500.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs