| Assessment Year | 2012 |
|---|---|
| Principal Product | Transit Buses |
| NAICS | 336111: Automobile Manufacturing |
| SIC | 3711: Motor Vehicles and Passenger Car Bodies |
| Sales Range | $100 M to 500M |
| # of Employees | 497 |
| Plant Area |
309,500
ft2
|
| Annual Production | 463
units
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $190,404 | 3,231,889 |
kWh
|
$0.059 |
| Electricity Demand | $125,553 | 7,910 |
kW-mo/yr
|
$15.87 |
| Electricity Fees | $9,890 | - |
|
- |
| Natural Gas | $257,297 | 27,466 |
MMBtu
|
$9.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $62,728 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $1,185 | - | - | - |
$1,185
-
MMBtu
|
- | - | |
| 02 | 2.7314: Reduce ventilation air | $7,403 | $5,019 |
$188
6,178
kWh
|
$468
-
kW-mo/yr
|
$6,747
-
MMBtu
|
- | - | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $18,749 | $42,038 |
$(-1,965.0)
(-34,595)
kWh
|
$(-653.0)
-
kW-mo/yr
|
$21,367
-
MMBtu
|
- | - | |
| 04 | 2.6211: Conserve energy by efficient use of vending machines | $391 | $1,332 |
$391
8,524
kWh
|
- | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,671 | $37,046 |
$4,892
109,471
kWh
|
$4,749
-
kW-mo/yr
|
- | $303 | $727 | |
| 06 | 3.1182: Make a new by-product | $21,685 | $100,000 |
$(-799.0)
(-14,290)
kWh
|
$(-3,635.0)
-
kW-mo/yr
|
- | - | $26,119 | |
| 07 | 3.1161: Eliminate/reduce an operation | $2,644 | $15,840 |
$(-164.0)
(-3,438)
kWh
|
$(-6,075.0)
-
kW-mo/yr
|
- | $2,098 | $6,785 | |
| TOTAL RECOMMENDED | $62,728 | $201,275 |
$2,543
71,850
kWh
|
$(-5,146.0)
-
kW-mo/yr
|
$29,299
-
MMBtu
|
$2,401 | $33,631 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs