ITAC Assessment: SD0418
ITAC logo
ITAC Assessment: SD0418
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product louvers
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 80,000
ft2
Annual Production 150,000
pieces
Production Hrs. Annual 2,152
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,641 671,477
kWh
Electricity Demand $25,337 2,635
kW-mo/yr
Electricity Fees $9,969 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,494 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $205

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,279 $5,868 $1,279
11,665
kWh
-
02 2.7135: Install occupancy sensors $205 $246 $205
1,872
kWh
-
03 2.7261: Install timers and/or thermostats $1,671 $500 $1,671
11,700
kWh
-
04 2.4133: Use most efficient type of electric motors $1,141 $4,207 $763
6,960
kWh
$378
-
kW-mo/yr
05 2.4231: Reduce the pressure of compressed air to the minimum required $198 - $198
1,805
kWh
-
TOTAL RECOMMENDED $4,494 $10,821 $4,116
34,002
kWh
$378
-
kW-mo/yr
TOTAL IMPLEMENTED $205 $246 $205
1,872
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs