| Assessment Year | 2004 |
|---|---|
| Principal Product | fasteners |
| NAICS | 332722: Bolt, Nut, Screw, Rivet, and Washer Manufacturing |
| SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
| Sales Range | $10 M to 50M |
| # of Employees | 225 |
| Plant Area |
200,000
ft2
|
| Annual Production | 0
pieces
|
| Production Hrs. Annual | 5,250
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $412,395 | 5,476,152 |
kWh
|
$0.075 |
| Electricity Demand | $175,259 | 18,439 |
kW-mo/yr
|
$9.50 |
| Natural Gas | $58,405 | 9,088 |
MMBtu
|
$6.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $320,126 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $132,869 | $208,000 |
$152,600
2,521,800
kWh
|
$17,100
-
kW-mo/yr
|
$(-36,831.0)
-
MMBtu
|
- | - | - | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $30,060 | $22,746 |
$25,804
342,675
kWh
|
$4,256
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $26,802 | $24,875 |
$29,277
388,800
kWh
|
$18,430
-
kW-mo/yr
|
$(-20,905.0)
-
MMBtu
|
- | - | - | |
| 04 | 2.2442: Preheat combustion air with waste heat | $8,450 | $18,000 | - | - |
$8,450
-
MMBtu
|
- | - | - | |
| 05 | 2.2511: Insulate bare equipment | $7,120 | $470 |
$7,120
94,560
kWh
|
- | - | - | - | - | |
| 06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $6,459 | $7,965 |
$4,749
63,073
kWh
|
$1,710
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,900 | $680 |
$4,579
60,783
kWh
|
$1,321
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,277 | $6,920 |
$2,277
30,242
kWh
|
- | - | - | - | - | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $870 | $1,795 |
$870
11,548
kWh
|
- | - | - | - | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,752 | $45,723 |
$11,341
150,615
kWh
|
$3,411
-
kW-mo/yr
|
- | - | - | - | |
| 11 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $6,792 | $10,000 | - | - | - |
$6,792
-
lb
|
- | - | |
| 12 | 3.3131: Use evaporation to concentrate material | $4,375 | $450 | - | - | - | - |
$4,375
-
lb
|
- | |
| 13 | 3.2176: Increase use of automation | $73,400 | $70,000 | - | - | - | - | - | $73,400 | |
| TOTAL RECOMMENDED | $320,126 | $417,624 |
$238,617
3,664,096
kWh
|
$46,228
-
kW-mo/yr
|
$(-49,286.0)
-
MMBtu
|
$6,792
-
lb
|
$4,375
-
lb
|
$73,400 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs