| Assessment Year | 2003 |
|---|---|
| Principal Product | cable ties |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 19 |
| Plant Area |
25,000
ft2
|
| Annual Production | 894,000,000
pieces
|
| Production Hrs. Annual | 6,600
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $364,652 | 3,719,833 |
kWh
|
$0.098 |
| Electricity Demand | $122,685 | 9,473 |
kW-mo/yr
|
$12.95 |
| Natural Gas | $4,600 | 616 |
MMBtu
|
$7.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $159,147 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $43,478 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $37,042 | $41,000 |
$29,868
304,771
kWh
|
$7,174
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $30,015 | - |
$24,304
247,998
kWh
|
$5,711
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7145: Install skylights | $14,068 | $6,000 |
$7,479
76,320
kWh
|
$6,589
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $11,373 | $19,250 |
$11,373
100,200
kWh
|
- | - | - | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $10,024 | $2,500 |
$5,284
53,913
kWh
|
$4,740
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4323: Use optimum size and capacity equipment | $6,436 | $1,116 |
$6,436
65,670
kWh
|
- | - | - | - | |
| 07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,039 | - | - |
$893
-
kW-mo/yr
|
$146 | - | - | |
| 08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,150 | $5,000 | - | - | - |
$5,150
-
lb
|
- | |
| 09 | 4.111: Add equipment/ operators to reduce production bottleneck | $44,000 | $25,000 | - | - | - | - | $44,000 | |
| TOTAL RECOMMENDED | $159,147 | $99,866 |
$84,744
848,872
kWh
|
$25,107
-
kW-mo/yr
|
$146 |
$5,150
-
lb
|
$44,000 | ||
| TOTAL IMPLEMENTED | $43,478 | $42,116 |
$36,304
370,441
kWh
|
$7,174
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs