Assessment Year | 2001 |
---|---|
Principal Product | earplugs |
NAICS |
n/a
|
SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
150,000
ft2
|
Annual Production | 600,000,000
pieces
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $514,687 | 4,711,285 |
kWh
|
$0.11 |
Electricity Demand | $102,583 | 10,230 |
kW-mo/yr
|
$10.03 |
Electricity Fees | $2,077 | - |
|
- |
Natural Gas | $210,464 | 34,389 |
MMBtu
|
$6.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $413,357 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $222,600 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1211: Move boiler to more efficient location | $40,607 | $10,000 |
$40,360
369,600
kWh
|
$9,629
-
kW-mo/yr
|
$(-9,382.0)
-
MMBtu
|
- | - | - | |
02 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $92,095 | $50,000 |
$73,850
676,279
kWh
|
$18,245
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.6218: Turn off equipment when not in use | $26,840 | $4,000 | - | - |
$26,840
-
MMBtu
|
- | - | - | |
04 | 2.2622: Replace existing chiller with high efficiency model | $7,953 | $16,000 |
$5,613
51,400
kWh
|
$2,340
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2437: Recover waste heat from equipment | $4,448 | $2,060 | - | - |
$4,448
-
MMBtu
|
- | - | - | |
06 | 2.1211: Move boiler to more efficient location | $10,321 | $17,000 |
$8,649
79,200
kWh
|
$3,611
-
kW-mo/yr
|
$(-1,939.0)
-
MMBtu
|
- | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,700 | $15,000 | - | - | - | - | $7,700 | - | |
08 | 4.446: Automate finishing process | $145,400 | $150,000 | - | - | - | $145,400 | - | - | |
09 | 4.446: Automate finishing process | $77,200 | $80,000 | - | - | - | $77,200 | - | - | |
10 | 4.821: Pay bills on time to avoid late fees | $793 | - | - | - | - | - | - | $793 | |
TOTAL RECOMMENDED | $413,357 | $344,060 |
$128,472
1,176,479
kWh
|
$33,825
-
kW-mo/yr
|
$19,967
-
MMBtu
|
$222,600 | $7,700 | $793 | ||
TOTAL IMPLEMENTED | $222,600 | $230,000 | - | - | - | $222,600 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs