ITAC Assessment: SD0263
ITAC logo
ITAC Assessment: SD0263
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Spas
NAICS
n/a
SIC 3088: Plastics Plumbing Fixtures
Sales Range $10
M
to 50
M
# of Employees 275
Plant Area 130,000
ft2
Annual Production 11,500
pieces
Production Hrs. Annual 4,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $160,392 1,495,500
kWh
Electricity Demand $48,905 5,354
kW-mo/yr
Electricity Fees $518 -
Natural Gas $25,211 3,906
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $88,870 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,255

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $8,376 $20,000 $3,558
33,250
kWh
$3,835
-
kW-mo/yr
$983
-
MMBtu
- -
02 2.6218: Turn off equipment when not in use $1,258 $1,500 $1,258
22,872
kWh
- - - -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,173 $4,000 $2,568
24,000
kWh
$1,315
-
kW-mo/yr
$(-710.0)
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,402 $90 $1,130
10,557
kWh
$272
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,644 $9,576 $4,208
39,330
kWh
$1,436
-
kW-mo/yr
- - -
06 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $3,239 $4,250 $2,149
20,080
kWh
$1,090
-
kW-mo/yr
- - -
07 3.8132: Use less toxic and volatile solvent substitutes $4,278 - - - - $4,278
-
gal
-
08 4.446: Automate finishing process $52,000 $60,000 - - - - $52,000
09 4.514: Re-arrange equipment layout to reduce handling costs $9,500 $7,000 - - - - $9,500
TOTAL RECOMMENDED $88,870 $106,416 $14,871
150,089
kWh
$7,948
-
kW-mo/yr
$273
-
MMBtu
$4,278
-
gal
$61,500
TOTAL IMPLEMENTED $25,255 $22,166 $9,164
96,759
kWh
$3,023
-
kW-mo/yr
$(-710.0)
-
MMBtu
$4,278
-
gal
$9,500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs