Assessment Year | 2001 |
---|---|
Principal Product | Spas |
NAICS |
n/a
|
SIC | 3088: Plastics Plumbing Fixtures |
Sales Range | $10 M to 50M |
# of Employees | 275 |
Plant Area |
130,000
ft2
|
Annual Production | 11,500
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $160,392 | 1,495,500 |
kWh
|
$0.11 |
Electricity Demand | $48,905 | 5,354 |
kW-mo/yr
|
$9.13 |
Electricity Fees | $518 | - |
|
- |
Natural Gas | $25,211 | 3,906 |
MMBtu
|
$6.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $88,870 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,255 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $8,376 | $20,000 |
$3,558
33,250
kWh
|
$3,835
-
kW-mo/yr
|
$983
-
MMBtu
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $1,258 | $1,500 |
$1,258
22,872
kWh
|
- | - | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,173 | $4,000 |
$2,568
24,000
kWh
|
$1,315
-
kW-mo/yr
|
$(-710.0)
-
MMBtu
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,402 | $90 |
$1,130
10,557
kWh
|
$272
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,644 | $9,576 |
$4,208
39,330
kWh
|
$1,436
-
kW-mo/yr
|
- | - | - | |
06 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $3,239 | $4,250 |
$2,149
20,080
kWh
|
$1,090
-
kW-mo/yr
|
- | - | - | |
07 | 3.8132: Use less toxic and volatile solvent substitutes | $4,278 | - | - | - | - |
$4,278
-
gal
|
- | |
08 | 4.446: Automate finishing process | $52,000 | $60,000 | - | - | - | - | $52,000 | |
09 | 4.514: Re-arrange equipment layout to reduce handling costs | $9,500 | $7,000 | - | - | - | - | $9,500 | |
TOTAL RECOMMENDED | $88,870 | $106,416 |
$14,871
150,089
kWh
|
$7,948
-
kW-mo/yr
|
$273
-
MMBtu
|
$4,278
-
gal
|
$61,500 | ||
TOTAL IMPLEMENTED | $25,255 | $22,166 |
$9,164
96,759
kWh
|
$3,023
-
kW-mo/yr
|
$(-710.0)
-
MMBtu
|
$4,278
-
gal
|
$9,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs