Assessment Year | 2000 |
---|---|
Principal Product | metal plating |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
30,000
ft2
|
Annual Production | 70,000
pieces
|
Production Hrs. Annual | 6,375
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $121,045 | 1,975,967 |
kWh
|
$0.061 |
Electricity Demand | $91,161 | 15,206 |
kW-mo/yr
|
$6.00 |
Electricity Fees | $3,838 | - |
|
- |
Natural Gas | $57,157 | 12,942 |
MMBtu
|
$4.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $86,268 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,600 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $17,132 | $28,575 |
$10,372
169,109
kWh
|
$6,760
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4131: Size electric motors for peak operating efficiency | $8,431 | $7,000 |
$6,236
101,700
kWh
|
$2,195
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,270 | $3,300 |
$6,270
102,286
kWh
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,673 | $11,336 |
$3,810
62,134
kWh
|
$1,863
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $5,209 | $7,872 |
$2,634
43,083
kWh
|
$2,575
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.2511: Insulate bare equipment | $4,293 | $9,936 | - | - |
$4,293
-
MMBtu
|
- | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,087 | - |
$2,370
38,687
kWh
|
$1,717
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,753 | $1,300 |
$1,839
30,188
kWh
|
$1,553
-
kW-mo/yr
|
$(-639.0)
-
MMBtu
|
- | - | - | |
09 | 2.2414: Use waste heat from hot flue gases to preheat | $1,098 | $500 | - | - |
$1,098
-
MMBtu
|
- | - | - | |
10 | 2.2414: Use waste heat from hot flue gases to preheat | $953 | $2,425 | - | - |
$953
-
MMBtu
|
- | - | - | |
11 | 2.9112: Use solar heat to heat water | $536 | $1,200 | - | - |
$536
-
MMBtu
|
- | - | - | |
12 | 3.5242: Recover metals from spent solutions and recycle | $9,975 | $50,000 | - | - | - |
$9,975
-
lb
|
- | - | |
13 | 3.4111: Use closed cycle process to minimize waste water production | $17,848 | $35,000 | - | - | - | - | - |
$17,848
-
Tgal
|
|
14 | 4.651: Install back-up equipment | $2,010 | $1,000 | - | - | - | - | $2,010 | - | |
TOTAL RECOMMENDED | $86,268 | $159,444 |
$33,531
547,187
kWh
|
$16,663
-
kW-mo/yr
|
$6,241
-
MMBtu
|
$9,975
-
lb
|
$2,010 |
$17,848
-
Tgal
|
||
TOTAL IMPLEMENTED | $10,600 | $18,308 |
$2,634
43,083
kWh
|
$2,575
-
kW-mo/yr
|
$5,391
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs