ITAC Assessment: SD0242
ITAC logo
ITAC Assessment: SD0242
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Engine parts
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 103,800
ft2
Annual Production 125,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $113,330 2,051,290
kWh
Electricity Demand $93,583 7,303
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,477 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,835

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.7111: Reduce illumination to minimum necessary levels $14,399 $1,960 $5,176
93,600
kWh
$9,223
-
kW-mo/yr
- - - - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $14,283 $3,000 $11,916
215,416
kWh
$9,992
-
kW-mo/yr
$(-7,625.0)
-
MMBtu
- - - - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,568 - - - - - - $4,568 - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,903 - $1,001
18,171
kWh
$902
-
kW-mo/yr
- - - - - -
05 3.2121: Convert to electrostatic powder coating $42,700 $58,000 - - - $2,700
-
gal
- - $40,000 -
06 3.8211: Convert to aqueous cleaning system $8,347 - - - - $2,700
-
gal
- $5,647 - -
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,533 $8,500 - - - - - $2,533 - -
08 3.5131: Recycle white water $313 $400 - - - - - - - $313
-
Tgal
09 4.221: Use only amount of packaging material necessary $2,431 $3,294 - - - - $351
-
lb
$2,080 - -
TOTAL RECOMMENDED $91,477 $75,154 $18,093
327,187
kWh
$20,117
-
kW-mo/yr
$(-7,625.0)
-
MMBtu
$5,400
-
gal
$351
-
lb
$14,828 $40,000 $313
-
Tgal
TOTAL IMPLEMENTED $18,835 $10,460 $6,177
111,771
kWh
$10,125
-
kW-mo/yr
- - - $2,533 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs