Assessment Year | 2000 |
---|---|
Principal Product | Engine parts |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
103,800
ft2
|
Annual Production | 125,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $113,330 | 2,051,290 |
kWh
|
$0.055 |
Electricity Demand | $93,583 | 7,303 |
kW-mo/yr
|
$12.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,477 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,835 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $14,399 | $1,960 |
$5,176
93,600
kWh
|
$9,223
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $14,283 | $3,000 |
$11,916
215,416
kWh
|
$9,992
-
kW-mo/yr
|
$(-7,625.0)
-
MMBtu
|
- | - | - | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,568 | - | - | - | - | - | - | $4,568 | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,903 | - |
$1,001
18,171
kWh
|
$902
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 3.2121: Convert to electrostatic powder coating | $42,700 | $58,000 | - | - | - |
$2,700
-
gal
|
- | - | $40,000 | - | |
06 | 3.8211: Convert to aqueous cleaning system | $8,347 | - | - | - | - |
$2,700
-
gal
|
- | $5,647 | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,533 | $8,500 | - | - | - | - | - | $2,533 | - | - | |
08 | 3.5131: Recycle white water | $313 | $400 | - | - | - | - | - | - | - |
$313
-
Tgal
|
|
09 | 4.221: Use only amount of packaging material necessary | $2,431 | $3,294 | - | - | - | - |
$351
-
lb
|
$2,080 | - | - | |
TOTAL RECOMMENDED | $91,477 | $75,154 |
$18,093
327,187
kWh
|
$20,117
-
kW-mo/yr
|
$(-7,625.0)
-
MMBtu
|
$5,400
-
gal
|
$351
-
lb
|
$14,828 | $40,000 |
$313
-
Tgal
|
||
TOTAL IMPLEMENTED | $18,835 | $10,460 |
$6,177
111,771
kWh
|
$10,125
-
kW-mo/yr
|
- | - | - | $2,533 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs