| Assessment Year | 2017 |
|---|---|
| Principal Product | Powertrain Components |
| NAICS | 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 244 |
| Plant Area |
188,932
ft2
|
| Annual Production | 12,512,350
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,042,761 | 34,657,649 |
kWh
|
$0.030 |
| Electricity Demand | $1,551,153 | 61,328 |
kW-mo/yr
|
$25.29 |
| Electricity Fees | $18,619 | - |
|
- |
| Natural Gas | $40,330 | 6,063 |
MMBtu
|
$6.65 |
| TOTAL YEARLY COSTS | $2,652,863 | |||
| RECOMMENDED SAVINGS* | $132,210 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $132,210 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4323: Use optimum size and capacity equipment | $1,211 | - |
$562
18,720
kWh
|
$649
-
kW-mo/yr
|
- | - | |
| 02 | 2.6218: Turn off equipment when not in use | $876 | - |
$876
29,212
kWh
|
- | - | - | |
| 03 | 4.821: Pay bills on time to avoid late fees | $7,288 | - | - | - | - | $7,288 | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $546 | $31 |
$203
6,780
kWh
|
$343
-
kW-mo/yr
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $635 | $42 |
$635
21,168
kWh
|
- | - | - | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $8,898 | $1,119 |
$6,344
211,467
kWh
|
- |
$2,554
-
MMBtu
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $112,756 | $41,810 |
$41,979
1,399,307
kWh
|
$70,777
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $132,210 | $43,002 |
$50,599
1,686,654
kWh
|
$71,769
-
kW-mo/yr
|
$2,554
-
MMBtu
|
$7,288 | ||
| TOTAL IMPLEMENTED | $132,210 | $43,002 |
$50,599
1,686,654
kWh
|
$71,769
-
kW-mo/yr
|
$2,554
-
MMBtu
|
$7,288 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs