Assessment Year | 2022 |
---|---|
Principal Product | Bread |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
380,000
ft2
|
Annual Production | 126,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $703,598 | 14,871,120 |
kWh
|
$0.047 | |
Electricity Demand | $131,395 | 25,024 |
kW-mo/yr
|
$5.25 | |
Electricity Fees | $125,179 | - |
|
- | |
Natural Gas | $769,180 | 99,246 |
MMBtu
|
$7.75 | |
Waste Disposal Costs | |||||
Water Usage | $45,728 | 4,726 |
Tgal
|
$9.68 | |
Water Disposal | $30,473 | 1,771 |
Tgal
|
$17.21 | |
Other Liquid (non-haz) | $262,666 | 3,719,340 |
gal
|
$0.071 | |
TOTAL YEARLY COSTS | $2,068,219 | ||||
RECOMMENDED SAVINGS* | $306,563 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $33,801 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,791 | - |
$1,553
33,046
kWh
|
$238
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,036 | $2,440 |
$3,499
74,457
kWh
|
$537
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,974 | $35,815 |
$24,189
514,667
kWh
|
$3,785
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2442: Preheat combustion air with waste heat | $28,034 | $80,000 | - | - |
$28,034
-
MMBtu
|
- | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,556 | $15,000 | - | - |
$4,556
-
MMBtu
|
- | - | - | |
06 | 3.1181: Eliminate a by-product | $188,025 | $700,000 |
$(-2,419.0)
(-51,450)
kWh
|
- | - |
$(-63,229.0)
-
Tgal
|
$264,073
-
gal
|
$(-10,400.0) | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $52,147 | $200,000 |
$47,264
1,005,618
kWh
|
$4,883
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $306,563 | $1,033,255 |
$74,086
1,576,338
kWh
|
$9,443
-
kW-mo/yr
|
$32,590
-
MMBtu
|
$(-63,229.0)
-
Tgal
|
$264,073
-
gal
|
$(-10,400.0) | ||
TOTAL IMPLEMENTED | $33,801 | $38,255 |
$29,241
622,170
kWh
|
$4,560
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs