ITAC Assessment: SD0235
ITAC logo
ITAC Assessment: SD0235
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product paint and coatings
NAICS
n/a
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 91,250
ft2
Annual Production 485
Tgal
Production Hrs. Annual 2,677
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,730 1,049,824
kWh
Electricity Demand $41,676 5,251
kW-mo/yr
Natural Gas $493 69
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $220,375 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $48,333

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Administrative Changes Savings
01 2.7144: Install spectral reflectors / delamp $3,382 $7,776 $2,436
31,653
kWh
$946
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,361 $1,782 $980
12,896
kWh
$381
-
kW-mo/yr
- - -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $3,356 - $2,294
29,894
kWh
$1,062
-
kW-mo/yr
- - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,218 $23,830 $5,530
74,443
kWh
$12,688
-
kW-mo/yr
- - -
05 2.6231: Utilize controls to operate equipment only when needed $5,852 - $5,852
76,202
kWh
- - - -
06 2.2612: Use cooling tower water instead of refrigeration $3,794 $14,000 $2,595
33,705
kWh
$1,199
-
kW-mo/yr
- - -
07 4.311: Schedule deliveries according to demand $7,690 - - - - - $7,690
08 3.7212: Improved material handling (mixing and transfer) $594 - - - - $594
-
lb
-
09 3.8143: Recycle cleaning solvent and reuse $34,580 $20,000 - - $34,580
-
gal
- -
10 4.111: Add equipment/ operators to reduce production bottleneck $107,143 $115,000 - - - - $107,143
11 2.3131: Reschedule plant operations or reduce load to avoid peaks $21,793 - - $21,793
-
kW-mo/yr
- - -
12 4.211: Consider use / purchase of bulk materials where possible $4,290 $8,840 - - - - $4,290
13 4.211: Consider use / purchase of bulk materials where possible $3,960 - - - - - $3,960
14 2.3132: Recharge batteries on during off-peak demand periods $4,362 $1,078 - $4,362
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $220,375 $192,306 $19,687
258,793
kWh
$42,431
-
kW-mo/yr
$34,580
-
gal
$594
-
lb
$123,083
TOTAL IMPLEMENTED $48,333 $24,908 $5,530
74,443
kWh
$38,843
-
kW-mo/yr
- - $3,960
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs