ITAC Assessment: SD0219
ITAC logo
ITAC Assessment: SD0219
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Distillated chemicals for semi-conductors
NAICS
n/a
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 228
Plant Area 62,051
ft2
Annual Production 55
Tgal
Production Hrs. Annual 6,120
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $378,141 8,064,478
kWh
Electricity Demand $244,026 14,938
kW-mo/yr
Natural Gas $69,732 14,973
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $131,159 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $113,572

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,370 $68,000 $7,615
162,368
kWh
$12,755
-
kW-mo/yr
- - - - -
02 2.2628: Utilize a less expensive cooling method $2,464 $3,500 $1,370
29,308
kWh
$1,094
-
kW-mo/yr
- - - - -
03 2.7111: Reduce illumination to minimum necessary levels $412 $144 $245
5,275
kWh
$167
-
kW-mo/yr
- - - - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $6,142 $2,500 $6,442
137,456
kWh
$2,430
-
kW-mo/yr
$(-2,730.0)
-
MMBtu
- - - -
05 2.2414: Use waste heat from hot flue gases to preheat $8,981 $9,500 $6,006
123,681
kWh
$2,975
-
kW-mo/yr
- - - - -
06 3.8133: Convert to aqueous cleaning $11,000 - - - - $11,000
-
gal
- - -
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,400 $2,000 - - - - - $5,400
-
lb
-
08 3.6193: Install equipment (eg compactor) to reduce disposal costs $11,118 $2,000 - - - - $11,118
-
lb
- -
09 4.446: Automate finishing process $58,252 $11,700 - - - - - - $58,252
10 4.311: Schedule deliveries according to demand $7,020 - - - - - - - $7,020
TOTAL RECOMMENDED $131,159 $99,344 $21,678
458,088
kWh
$19,421
-
kW-mo/yr
$(-2,730.0)
-
MMBtu
$11,000
-
gal
$11,118
-
lb
$5,400
-
lb
$65,272
TOTAL IMPLEMENTED $113,572 $83,844 $7,860
167,643
kWh
$12,922
-
kW-mo/yr
- $11,000
-
gal
$11,118
-
lb
$5,400
-
lb
$65,272
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs