| Assessment Year | 1999 |
|---|---|
| Principal Product | Distillated chemicals for semi-conductors |
| NAICS |
n/a
|
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 228 |
| Plant Area |
62,051
ft2
|
| Annual Production | 55
Tgal
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $378,141 | 8,064,478 |
kWh
|
$0.047 |
| Electricity Demand | $244,026 | 14,938 |
kW-mo/yr
|
$16.34 |
| Natural Gas | $69,732 | 14,973 |
MMBtu
|
$4.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $131,159 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $113,572 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $20,370 | $68,000 |
$7,615
162,368
kWh
|
$12,755
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.2628: Utilize a less expensive cooling method | $2,464 | $3,500 |
$1,370
29,308
kWh
|
$1,094
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $412 | $144 |
$245
5,275
kWh
|
$167
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,142 | $2,500 |
$6,442
137,456
kWh
|
$2,430
-
kW-mo/yr
|
$(-2,730.0)
-
MMBtu
|
- | - | - | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $8,981 | $9,500 |
$6,006
123,681
kWh
|
$2,975
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 3.8133: Convert to aqueous cleaning | $11,000 | - | - | - | - |
$11,000
-
gal
|
- | - | - | |
| 07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,400 | $2,000 | - | - | - | - | - |
$5,400
-
lb
|
- | |
| 08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $11,118 | $2,000 | - | - | - | - |
$11,118
-
lb
|
- | - | |
| 09 | 4.446: Automate finishing process | $58,252 | $11,700 | - | - | - | - | - | - | $58,252 | |
| 10 | 4.311: Schedule deliveries according to demand | $7,020 | - | - | - | - | - | - | - | $7,020 | |
| TOTAL RECOMMENDED | $131,159 | $99,344 |
$21,678
458,088
kWh
|
$19,421
-
kW-mo/yr
|
$(-2,730.0)
-
MMBtu
|
$11,000
-
gal
|
$11,118
-
lb
|
$5,400
-
lb
|
$65,272 | ||
| TOTAL IMPLEMENTED | $113,572 | $83,844 |
$7,860
167,643
kWh
|
$12,922
-
kW-mo/yr
|
- |
$11,000
-
gal
|
$11,118
-
lb
|
$5,400
-
lb
|
$65,272 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs