ITAC Assessment: SD0216
ITAC logo
ITAC Assessment: SD0216
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product metal plating
NAICS
n/a
SIC 3462: Iron and Steel Forgings
Sales Range $5
M
to 10
M
# of Employees 78
Plant Area
n/a
Annual Production 48,000
pieces
Production Hrs. Annual 6,732
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $205,062 2,948,124
kWh
Electricity Demand $61,509 7,742
kW-mo/yr
Natural Gas $13,252 2,094
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $157,758 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,078

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7144: Install spectral reflectors / delamp $1,277 $1,650 $843
12,016
kWh
$434
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $11,961 $1,060 $9,906
142,438
kWh
$2,055
-
kW-mo/yr
- - - -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $99,648 $111,600 $107,328
1,542,497
kWh
$50,308
-
kW-mo/yr
$(-57,988.0)
-
MMBtu
- - -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $840 - - - - - - $840
05 3.3131: Use evaporation to concentrate material $1,038 $1,500 - - - - $1,038
-
lb
-
06 3.8133: Convert to aqueous cleaning $6,009 $6,009 - - - $6,009
-
gal
- -
07 4.446: Automate finishing process $11,740 $4,100 - - - - - $11,740
08 4.514: Re-arrange equipment layout to reduce handling costs $25,245 $22,970 - - - - - $25,245
TOTAL RECOMMENDED $157,758 $148,889 $118,077
1,696,951
kWh
$52,797
-
kW-mo/yr
$(-57,988.0)
-
MMBtu
$6,009
-
gal
$1,038
-
lb
$37,825
TOTAL IMPLEMENTED $14,078 $2,710 $10,749
154,454
kWh
$2,489
-
kW-mo/yr
- - - $840
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs