| Assessment Year | 1998 |
|---|---|
| Principal Product | Filtration systems |
| NAICS |
n/a
|
| SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
| Sales Range | $10 M to 50M |
| # of Employees | 270 |
| Plant Area |
110,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,600
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $142,320 | 3,228,312 |
kWh
|
$0.044 |
| Electricity Demand | $134,152 | 8,202 |
kW-mo/yr
|
$16.36 |
| Natural Gas | $95,023 | 17,418 |
MMBtu
|
$5.46 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $495,129 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,218 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2425: Use flue gases to heat process or service water | $78,408 | $16,000 | - | - |
$78,408
-
MMBtu
|
- | - | |
| 02 | 2.1117: Relocate oven / furnace to more efficient location | $36,215 | $3,000 |
$21,606
491,208
kWh
|
$14,609
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.1117: Relocate oven / furnace to more efficient location | $10,888 | $2,500 |
$5,227
118,992
kWh
|
$5,661
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,843 | $2,700 |
$1,634
37,222
kWh
|
$2,209
-
kW-mo/yr
|
- | - | - | |
| 05 | 3.5131: Recycle white water | $12,375 | $5,000 | - | - | - |
$12,375
-
Tgal
|
- | |
| 06 | 4.111: Add equipment/ operators to reduce production bottleneck | $353,400 | $310,000 | - | - | - | - |
$353,400
-
Tgal
|
|
| TOTAL RECOMMENDED | $495,129 | $339,200 |
$28,467
647,422
kWh
|
$22,479
-
kW-mo/yr
|
$78,408
-
MMBtu
|
$12,375
-
Tgal
|
$353,400
-
Tgal
|
||
| TOTAL IMPLEMENTED | $16,218 | $7,700 |
$1,634
37,222
kWh
|
$2,209
-
kW-mo/yr
|
- |
$12,375
-
Tgal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs