ITAC Assessment: NL0097
ITAC logo
ITAC Assessment: NL0097
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Plastic Siding
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 39
Plant Area 155,829
ft2
Annual Production 9,568
ton
Production Hrs. Annual 2,496
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $362,627 5,288,504
kWh
Electricity Demand $328,607 26,852
kW-mo/yr
Electricity Fees $1,629 -
Natural Gas $95,173 14,430
MMBtu
Other Gas $12,864 1
MMBtu
Waste Disposal Costs
Water Usage $909 8,452
Tgal
Water Disposal $941 8,452
Tgal
Other Liquid (non-haz) $17,229 1
gal
TOTAL YEARLY COSTS $819,979
RECOMMENDED SAVINGS* $38,508 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4239: Eliminate or reduce compressed air usage $13,785 $3,000 $11,016
159,666
kWh
$2,768
-
kW-mo/yr
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,684 $3,900 $8,184
118,615
kWh
- - - $(-400.0) $(-100.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,735 $10,810 $2,134
30,926
kWh
$787
-
kW-mo/yr
- - $1,046 $3,768
04 2.8121: Apply for tax-free status for energy purchases $3,054 $2,080 - - $2,836
-
MMBtu
$218
-
gal
- -
05 2.4221: Install compressor air intakes in coolest locations $2,556 $1,315 $2,556
37,043
kWh
- - - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $2,203 $120 $2,203
31,932
kWh
- - - - -
07 2.7135: Install occupancy sensors $1,210 $1,348 $1,210
17,543
kWh
- - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $281 $422 $94
1,367
kWh
$23
-
kW-mo/yr
- - $164 -
TOTAL RECOMMENDED $38,508 $22,995 $27,397
397,092
kWh
$3,578
-
kW-mo/yr
$2,836
-
MMBtu
$218
-
gal
$810 $3,668
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs