ITAC Assessment: SD0174
ITAC logo
ITAC Assessment: SD0174
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Transformers, inductors and electric components for major in
NAICS
n/a
SIC 3677: Electronic Coils, Transformers, and Other Inductors
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 27,000
ft2
Annual Production 3,200
pieces
Production Hrs. Annual 2,167
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,407 1,009,672
kWh
Electricity Demand $28,948 3,566
kW-mo/yr
Natural Gas $1,991 263
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,746 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,349

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.4226: Use / purchase optimum sized compressor $721 $1,200 $558
6,741
kWh
$163
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,934 $17,722 $6,327
77,081
kWh
$2,607
-
kW-mo/yr
- -
03 2.7144: Install spectral reflectors / delamp $15,429 $16,085 $10,936
133,353
kWh
$4,493
-
kW-mo/yr
- -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,120 $2,000 - - - $3,120
05 3.8224: Convert to less toxic hydrocarbon cleaners $4,145 - - - $4,145
-
gal
-
06 3.1175: Use a different or recycled raw material $2,397 $320 - - - $2,397
TOTAL RECOMMENDED $34,746 $37,327 $17,821
217,175
kWh
$7,263
-
kW-mo/yr
$4,145
-
gal
$5,517
TOTAL IMPLEMENTED $32,349 $37,007 $17,821
217,175
kWh
$7,263
-
kW-mo/yr
$4,145
-
gal
$3,120
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs