Assessment Year | 1996 |
---|---|
Principal Product | Bath Tubs |
NAICS |
n/a
|
SIC | 3083: Laminated Plastics Plate, Sheet, and Profile Shapes |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
125,000
ft2
|
Annual Production | 125,000
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $288,542 | 4,046,600 |
kWh
|
$0.071 |
Electricity Demand | $149,810 | 16,265 |
kW-mo/yr
|
$9.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $450,256 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $450,256 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $3,217 | $3,300 |
$2,390
33,705
kWh
|
$827
-
kW-mo/yr
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,369 | - |
$1,001
14,068
kWh
|
$368
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,422 | $650 |
$3,237
45,721
kWh
|
$1,185
-
kW-mo/yr
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $24,199 | $1,500 |
$13,147
185,229
kWh
|
$11,052
-
kW-mo/yr
|
- | - | - | |
05 | 2.7261: Install timers and/or thermostats | $2,716 | $900 |
$2,716
38,394
kWh
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,237 | $2,754 |
$1,237
11,723
kWh
|
- | - | - | - | |
07 | 2.7144: Install spectral reflectors / delamp | $3,369 | $4,110 |
$3,369
32,532
kWh
|
- | - | - | - | |
08 | 2.7135: Install occupancy sensors | $3,812 | $1,476 |
$3,812
37,808
kWh
|
- | - | - | - | |
09 | 4.122: Develop standard procedures to improve internal yields | $50,000 | - | - | - | - |
$50,000
-
lb
|
- | |
10 | 3.8224: Convert to less toxic hydrocarbon cleaners | $12,265 | - | - | - |
$12,265
-
gal
|
- | - | |
11 | 3.7198: Reduce / eliminate use of disposable product | $2,250 | $1,100 | - | - | - | - | $2,250 | |
12 | 3.1191: Change procedures / equipment / operating conditions | $45,000 | $3,500 | - | - | - |
$45,000
-
lb
|
- | |
13 | 3.1191: Change procedures / equipment / operating conditions | $296,400 | $20,000 | - | - | - | - | $296,400 | |
TOTAL RECOMMENDED | $450,256 | $39,290 |
$30,909
399,180
kWh
|
$13,432
-
kW-mo/yr
|
$12,265
-
gal
|
$95,000
-
lb
|
$298,650 | ||
TOTAL IMPLEMENTED | $450,256 | $39,290 |
$30,909
399,180
kWh
|
$13,432
-
kW-mo/yr
|
$12,265
-
gal
|
$95,000
-
lb
|
$298,650 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs