ITAC Assessment: SD0165
ITAC logo
ITAC Assessment: SD0165
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Bath Tubs
NAICS
n/a
SIC 3083: Laminated Plastics Plate, Sheet, and Profile Shapes
Sales Range $50
M
to 100
M
# of Employees 350
Plant Area 125,000
ft2
Annual Production 125,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $288,542 4,046,600
kWh
Electricity Demand $149,810 16,265
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $450,256 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $450,256

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $3,217 $3,300 $2,390
33,705
kWh
$827
-
kW-mo/yr
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,369 - $1,001
14,068
kWh
$368
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,422 $650 $3,237
45,721
kWh
$1,185
-
kW-mo/yr
- - -
04 2.2511: Insulate bare equipment $24,199 $1,500 $13,147
185,229
kWh
$11,052
-
kW-mo/yr
- - -
05 2.7261: Install timers and/or thermostats $2,716 $900 $2,716
38,394
kWh
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,237 $2,754 $1,237
11,723
kWh
- - - -
07 2.7144: Install spectral reflectors / delamp $3,369 $4,110 $3,369
32,532
kWh
- - - -
08 2.7135: Install occupancy sensors $3,812 $1,476 $3,812
37,808
kWh
- - - -
09 4.122: Develop standard procedures to improve internal yields $50,000 - - - - $50,000
-
lb
-
10 3.8224: Convert to less toxic hydrocarbon cleaners $12,265 - - - $12,265
-
gal
- -
11 3.7198: Reduce / eliminate use of disposable product $2,250 $1,100 - - - - $2,250
12 3.1191: Change procedures / equipment / operating conditions $45,000 $3,500 - - - $45,000
-
lb
-
13 3.1191: Change procedures / equipment / operating conditions $296,400 $20,000 - - - - $296,400
TOTAL RECOMMENDED $450,256 $39,290 $30,909
399,180
kWh
$13,432
-
kW-mo/yr
$12,265
-
gal
$95,000
-
lb
$298,650
TOTAL IMPLEMENTED $450,256 $39,290 $30,909
399,180
kWh
$13,432
-
kW-mo/yr
$12,265
-
gal
$95,000
-
lb
$298,650
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs