ITAC Assessment: SD0157
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Chemical miling of quarts materials for computer communicati
NAICS
n/a
SIC 3541: Machine Tools, Metal Cutting Types
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 40,000
ft2
Annual Production 3,000,000
units
Production Hrs. Annual 2,423
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $239,563 3,028,136
kWh
Electricity Demand $51,512 7,099
kW-mo/yr
Natural Gas $6,014 983
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,661 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,963

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Liquid (haz) Savings
01 2.4133: Use most efficient type of electric motors $2,138 $1,520 $2,138
21,981
kWh
-
02 2.7145: Install skylights $3,034 $6,096 $3,034
22,567
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $970 $950 $970
10,551
kWh
-
04 2.6231: Utilize controls to operate equipment only when needed $1,120 $300 $1,120
14,361
kWh
-
05 2.6218: Turn off equipment when not in use $503 $300 $503
6,448
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,289 $1,968 $2,289
22,567
kWh
-
07 2.7144: Install spectral reflectors / delamp $9,864 $13,875 $9,864
96,131
kWh
-
08 2.7135: Install occupancy sensors $1,743 $1,255 $1,743
16,413
kWh
-
09 3.1191: Change procedures / equipment / operating conditions $800 $1,000 - $800
-
gal
10 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,200 $1,000 - $3,200
-
gal
TOTAL RECOMMENDED $25,661 $28,264 $21,661
211,019
kWh
$4,000
-
gal
TOTAL IMPLEMENTED $11,963 $7,293 $8,763
92,321
kWh
$3,200
-
gal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Other Liquid (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs