ITAC Assessment: SD0153
ITAC logo
ITAC Assessment: SD0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Cylinder Heads and Other Parts for Aircraft
NAICS
n/a
SIC 3440:
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 70,000
ft2
Annual Production 146,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $338,705 4,708,382
kWh
Electricity Demand $130,728 13,128
kW-mo/yr
Electricity Fees $469,433 -
Natural Gas $97,661 22,706
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $88,069 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $88,069

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $4,983 $4,130 $4,983
53,927
kWh
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,640 $350 - $2,640
-
kW-mo/yr
- - -
03 2.2614: Use cooling tower or economizer to replace chiller cooling $3,241 $4,860 $3,241
46,307
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $10,990 $11,477 - $10,990
-
kW-mo/yr
- - -
05 2.7144: Install spectral reflectors / delamp $8,674 $6,355 - $8,674
-
kW-mo/yr
- - -
06 2.7135: Install occupancy sensors $582 $484 - $582
-
kW-mo/yr
- - -
07 3.1244: Reduce solution drag-out to prevent solution loss $26,348 - - - $26,348
-
gal
- -
08 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,300 $9,000 - - - - $5,300
09 3.5131: Recycle white water $7,791 $750 - - $7,791
-
gal
- -
10 3.3122: Use filtration, centrifuging to remove contaminants $17,520 - - - - $17,520
-
gal
-
TOTAL RECOMMENDED $88,069 $37,406 $8,224
100,234
kWh
$22,886
-
kW-mo/yr
$34,139
-
gal
$17,520
-
gal
$5,300
TOTAL IMPLEMENTED $88,069 $37,406 $8,224
100,234
kWh
$22,886
-
kW-mo/yr
$34,139
-
gal
$17,520
-
gal
$5,300
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs