ITAC Assessment: SD0146
ITAC logo
ITAC Assessment: SD0146
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Chrome and Zinc Plated Products
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 38,000
ft2
Annual Production 150,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,547 3,556,858
kWh
Electricity Demand $98,011 9,806
kW-mo/yr
Natural Gas $107,546 16,004
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,368 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,368

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings
01 2.6231: Utilize controls to operate equipment only when needed $857 $150 $857
13,189
kWh
- -
02 2.2511: Insulate bare equipment $530 $659 - $530
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $515 $564 $515
7,913
kWh
- -
04 2.7144: Install spectral reflectors / delamp $373 $710 $373
5,275
kWh
- -
05 2.7135: Install occupancy sensors $595 $394 $595
9,086
kWh
- -
06 3.1244: Reduce solution drag-out to prevent solution loss $26,498 - - - $26,498
-
gal
TOTAL RECOMMENDED $29,368 $2,477 $2,340
35,463
kWh
$530
-
MMBtu
$26,498
-
gal
TOTAL IMPLEMENTED $29,368 $2,477 $2,340
35,463
kWh
$530
-
MMBtu
$26,498
-
gal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs