| Assessment Year | 1995 |
|---|---|
| Principal Product | Printed Circuit Boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
n/a
|
| Annual Production | 36,200
thousand feet
|
| Production Hrs. Annual | 6,552
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $138,982 | 1,190,797 |
kWh
|
$0.12 |
| Natural Gas | $2,772 | 389 |
MMBtu
|
$7.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,588 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,910 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,149 | $450 |
$1,149
9,965
kWh
|
- | - | |
| 02 | 2.2514: Cover open tanks | $1,015 | $250 |
$1,015
8,792
kWh
|
- | - | |
| 03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $1,144 | $1,600 |
$1,144
4,689
kWh
|
- | - | |
| 04 | 2.2511: Insulate bare equipment | $2,282 | $563 |
$2,282
19,637
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,168 | $6,733 |
$3,168
27,257
kWh
|
- | - | |
| 06 | 2.7144: Install spectral reflectors / delamp | $5,047 | $4,305 |
$5,047
41,032
kWh
|
- | - | |
| 07 | 2.7135: Install occupancy sensors | $494 | $599 |
$494
4,103
kWh
|
- | - | |
| 08 | 2.7261: Install timers and/or thermostats | $1,306 | $849 |
$1,306
11,137
kWh
|
- | - | |
| 09 | 3.1244: Reduce solution drag-out to prevent solution loss | $730 | $250 | - |
$730
-
gal
|
- | |
| 10 | 3.5314: Use in-process recycling whenever possible | $2,184 | - | - | - |
$2,184
-
lb
|
|
| 11 | 3.1152: Use high quality scrap (low sulfur) to reduce hazardous sludge generation | $1,069 | $1,000 | - |
$1,069
-
gal
|
- | |
| TOTAL RECOMMENDED | $19,588 | $16,599 |
$15,605
126,612
kWh
|
$1,799
-
gal
|
$2,184
-
lb
|
||
| TOTAL IMPLEMENTED | $16,910 | $16,000 |
$15,111
122,509
kWh
|
$1,799
-
gal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs