ITAC Assessment: SD0107
ITAC logo
ITAC Assessment: SD0107
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Metal Cans
NAICS
n/a
SIC 3411: Metal Cans
Sales Range $10
M
to 50
M
# of Employees 134
Plant Area 420,000
ft2
Annual Production 42,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $705,292 7,170,575
kWh
Natural Gas $373,846 89,612
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $199,252 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $172,749

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Water Disposal Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $8,588 $14,400 $8,588
87,339
kWh
- -
02 2.8114: Change rate schedules or other changes in utility service $94,795 $22,000 - - $94,795
03 2.4226: Use / purchase optimum sized compressor $9,603 $4,100 $9,603
97,597
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $32,270 $62,889 $32,270
325,029
kWh
- -
05 2.7144: Install spectral reflectors / delamp $25,421 $23,285 $25,421
240,621
kWh
- -
06 2.7135: Install occupancy sensors $2,466 $2,184 $2,466
23,154
kWh
- -
07 2.7111: Reduce illumination to minimum necessary levels $9,209 $1,260 $9,209
81,770
kWh
- -
08 3.4115: Recover and reuse cooling water $8,450 $5,000 - $8,450
-
Tgal
-
09 3.4115: Recover and reuse cooling water $8,450 $4,885 - $8,450
-
Tgal
-
TOTAL RECOMMENDED $199,252 $140,003 $87,557
855,510
kWh
$16,900
-
Tgal
$94,795
TOTAL IMPLEMENTED $172,749 $126,018 $77,954
757,913
kWh
- $94,795
Yearly Savings* Imp'd Cost* Electricity Usage Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs