ITAC Assessment: OK0489
ITAC logo
ITAC Assessment: OK0489
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Cooked sausages, hams, and meats
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 33,000
ft2
Annual Production 4,500,000
lb
Production Hrs. Annual 2,340
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,220 1,065,651
kWh
Electricity Demand $29,690 2,808
kW-mo/yr
Electricity Fees $3,250 -
Natural Gas $15,756 4,405
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,927 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $189

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings
01 2.1221: Replace obsolete burners with more efficient ones $10,738 $10,000 - $10,738
-
MMBtu
-
02 2.4314: Use synthetic lubricant $90 $155 $90
3,224
kWh
- -
03 3.1194: Use automatic flow control $16 $46 - - $16
-
Tgal
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $83 $30 $83
4,689
kWh
- -
TOTAL RECOMMENDED $10,927 $10,231 $173
7,913
kWh
$10,738
-
MMBtu
$16
-
Tgal
TOTAL IMPLEMENTED $189 $231 $173
7,913
kWh
- $16
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs