ITAC Assessment: SD0088
ITAC logo
ITAC Assessment: SD0088
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Transducers
NAICS
n/a
SIC 3829: Measuring and Controlling Devices, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 200,000
ft2
Annual Production 4,800
pieces
Production Hrs. Annual 2,168
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $579,645 6,729,191
kWh
Natural Gas $46,132 6,853
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $218,027 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $218,027

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $5,963 $4,300 $5,963
69,168
kWh
-
02 2.6231: Utilize controls to operate equipment only when needed $6,722 $200 $6,722
77,960
kWh
-
03 2.2511: Insulate bare equipment $376 $235 - $376
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,853 $150 $3,853
44,842
kWh
-
05 2.4323: Use optimum size and capacity equipment $117,014 $245,000 $117,014
1,358,148
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $40,436 $95,019 $40,436
445,193
kWh
-
07 2.7144: Install spectral reflectors / delamp $39,115 $43,220 $39,115
415,592
kWh
-
08 2.7132: Install timers on light switches in little used areas $4,548 $810 $4,548
45,721
kWh
-
TOTAL RECOMMENDED $218,027 $388,934 $217,651
2,456,624
kWh
$376
-
MMBtu
TOTAL IMPLEMENTED $218,027 $388,934 $217,651
2,456,624
kWh
$376
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs