ITAC Assessment: SD0064
ITAC logo
ITAC Assessment: SD0064
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product ANIMAL AND FOWL FOOD
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $10
M
to 50
M
# of Employees 71
Plant Area
n/a
Annual Production 208,000
ton
Production Hrs. Annual 5,616
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $271,233 2,699,883
kWh
Natural Gas $117,646 21,588
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,599 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,700

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $907 $1,038 $907
9,086
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,679 $5,291 $3,679
36,635
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,125 $60 $1,125
11,137
kWh
- -
04 2.6212: Turn off equipment during breaks, reduce operating time $795 $600 $795
7,913
kWh
- -
05 2.1232: Keep boiler tubes clean $4,163 $2,000 - $4,163
-
MMBtu
-
06 2.1131: Repair faulty insulation in furnaces, boilers, etc $1,928 $674 - $1,928
-
MMBtu
-
07 2.2136: Install / repair insulation on steam lines $216 $412 - $216
-
MMBtu
-
08 2.2515: Use optimum thickness insulation $193 $61 - $193
-
MMBtu
-
09 2.2515: Use optimum thickness insulation $255 $228 - $255
-
MMBtu
-
10 2.2441: Preheat boiler makeup water with waste process heat $12,485 $15,690 - $12,485
-
MMBtu
-
11 2.2449: Recover heat from exhausted steam, hot air or hot water $1,874 $1,256 - $1,874
-
MMBtu
-
12 2.7142: Utilize higher efficiency lamps and/or ballasts $1,459 $120 $1,559
15,533
kWh
- $(-100.0)
13 2.6232: Install set-back timers $174 $100 $174
1,465
kWh
- -
14 2.7134: Use photocell controls $1,543 $575 $1,443
14,361
kWh
- $100
15 2.6232: Install set-back timers $400 $760 $353
3,517
kWh
- $47
16 2.7142: Utilize higher efficiency lamps and/or ballasts $293 $24 $270
2,638
kWh
- $23
17 2.7492: Use proper thickness of insulation on building envelope $110 $174 $110
1,172
kWh
- -
TOTAL RECOMMENDED $31,599 $29,063 $10,415
103,457
kWh
$21,114
-
MMBtu
$70
TOTAL IMPLEMENTED $29,700 $28,128 $9,180
91,148
kWh
$20,450
-
MMBtu
$70
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs