Assessment Year | 1993 |
---|---|
Principal Product | PAINTS,THINNERS,COATINGS |
NAICS |
n/a
|
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $5 M to 10M |
# of Employees | 160 |
Plant Area |
n/a
|
Annual Production | 5,750,000
lb
|
Production Hrs. Annual | 5,500
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $284,257 | 2,415,006 |
kWh
|
$0.12 |
Natural Gas | $6,160 | 943 |
MMBtu
|
$6.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,825 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,599 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,064 | $2,242 |
$2,064
17,585
kWh
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,309 | $3,524 |
$2,309
19,637
kWh
|
- | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $13,057 | - |
$13,057
-
kWh
|
- | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $4,870 | $4,500 |
$4,870
41,325
kWh
|
- | |
05 | 2.6232: Install set-back timers | $226 | $115 |
$210
1,758
kWh
|
$16 | |
06 | 2.7144: Install spectral reflectors / delamp | $6,678 | $12,550 |
$5,691
48,359
kWh
|
$987 | |
07 | 2.6232: Install set-back timers | $3,621 | $3,920 |
$3,103
26,377
kWh
|
$518 | |
TOTAL RECOMMENDED | $32,825 | $26,851 |
$31,304
155,041
kWh
|
$1,521 | ||
TOTAL IMPLEMENTED | $32,599 | $26,736 |
$31,094
153,283
kWh
|
$1,505 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs