Assessment Year | 1993 |
---|---|
Principal Product | INDUSTRIAL LUBRICANTS |
NAICS |
n/a
|
SIC | 2992: Lubricating Oils and Greases |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
n/a
|
Annual Production | 5,500
Tgal
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $170,173 | 1,353,458 |
kWh
|
$0.13 |
Natural Gas | $79,094 | 22,258 |
MMBtu
|
$3.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,594 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $165 | $222 |
$165
1,172
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,255 | $4,329 |
$4,255
33,998
kWh
|
- | - | |
03 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $312 | $658 | - |
$312
-
MMBtu
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $1,571 | $654 | - |
$1,571
-
MMBtu
|
- | |
05 | 2.1242: Minimize boiler blowdown with better feedwater treatment | $9,280 | $2,450 | - |
$9,280
-
MMBtu
|
- | |
06 | 2.2113: Repair or replace steam traps | $14,542 | $6,550 | - |
$14,542
-
MMBtu
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,035 | $40 |
$3,035
24,033
kWh
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $434 | - |
$485
3,810
kWh
|
- | $(-51.0) | |
09 | 2.7144: Install spectral reflectors / delamp | $2,893 | $3,900 |
$2,563
20,516
kWh
|
- | $330 | |
10 | 2.6232: Install set-back timers | $903 | $1,240 |
$759
6,155
kWh
|
- | $144 | |
TOTAL RECOMMENDED | $37,390 | $20,043 |
$11,262
89,684
kWh
|
$25,705
-
MMBtu
|
$423 | ||
TOTAL IMPLEMENTED | $33,594 | $14,903 |
$7,940
63,013
kWh
|
$25,705
-
MMBtu
|
$(-51.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs