ITAC Assessment: SD0027
ITAC logo
ITAC Assessment: SD0027
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PLASTIC PLUMBING FIXTURE
NAICS
n/a
SIC 3088: Plastics Plumbing Fixtures
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area
n/a
Annual Production 24,350,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $170,988 2,009,965
kWh
Natural Gas $173 9
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,853 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,553

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $2,402 $1,720 $2,402
28,136
kWh
-
02 2.2511: Insulate bare equipment $3,784 $206 $3,784
44,549
kWh
-
03 2.2511: Insulate bare equipment $189 $18 $189
2,345
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $141 - $200
2,345
kWh
$(-59.0)
05 2.7123: Keep lamps and reflectors clean $2,111 $2,300 $1,866
21,981
kWh
$245
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,187 $700 $457
5,275
kWh
$730
07 2.6232: Install set-back timers $1,039 - $923
10,844
kWh
$116
TOTAL RECOMMENDED $10,853 $4,944 $9,821
115,475
kWh
$1,032
TOTAL IMPLEMENTED $8,553 $2,626 $7,766
91,149
kWh
$787
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs