Assessment Year | 1992 |
---|---|
Principal Product | RUBBER PRODUCTS |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
n/a
|
Annual Production | 50,000,000
pieces
|
Production Hrs. Annual | 6,375
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $151,525 | 1,672,626 |
kWh
|
$0.091 |
Natural Gas | $56,717 | 12,408 |
MMBtu
|
$4.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,748 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,038 | $575 |
$1,038
11,430
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,980 | $2,000 |
$15,980
176,436
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $654 | $15 |
$654
7,327
kWh
|
- | - | |
04 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $490 | $245 | - |
$490
-
MMBtu
|
- | |
05 | 2.2127: Flash condensate to produce lower pressure steam | $1,061 | $2,160 | - |
$1,061
-
MMBtu
|
- | |
06 | 2.2113: Repair or replace steam traps | $12,496 | $830 | - |
$12,496
-
MMBtu
|
- | |
07 | 2.2135: Repair and eliminate steam leaks | $9,999 | $200 | - |
$9,999
-
MMBtu
|
- | |
08 | 2.6232: Install set-back timers | $3,070 | $4,050 |
$3,040
35,756
kWh
|
- | $30 | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,607 | - |
$3,946
43,376
kWh
|
- | $(-339.0) | |
10 | 2.6231: Utilize controls to operate equipment only when needed | $3,353 | $200 |
$3,353
36,928
kWh
|
- | - | |
TOTAL RECOMMENDED | $51,748 | $10,275 |
$28,011
311,253
kWh
|
$24,046
-
MMBtu
|
$(-309.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs