ITAC Assessment: SD0015
ITAC logo
ITAC Assessment: SD0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product AEROSPCE SHT METALS COMP
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area
n/a
Annual Production 2,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $89,758 1,041,325
kWh
Natural Gas $19,451 3,030
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,866 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $312 $567 $312
3,517
kWh
- -
02 2.1221: Replace obsolete burners with more efficient ones $1,236 $3,800 - $1,236
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,822 $2,000 $3,822
44,256
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $647 $544 $365
4,103
kWh
- $282
05 2.6232: Install set-back timers $1,106 $1,650 $980
11,430
kWh
- $126
06 2.7123: Keep lamps and reflectors clean $9,743 $1,657 $8,680
100,821
kWh
- $1,063
TOTAL RECOMMENDED $16,866 $10,218 $14,159
164,127
kWh
$1,236
-
MMBtu
$1,471
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs