Assessment Year | 1992 |
---|---|
Principal Product | THERMOPLASTIC MOLDINGS |
NAICS |
n/a
|
SIC | 3432: Plumbing Fixture Fittings and Trim |
Sales Range | $1 M to 5M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $226,704 | 2,648,886 |
kWh
|
$0.086 |
Natural Gas | $4,298 | 653 |
MMBtu
|
$6.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,077 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,267 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,036 | - |
$2,036
23,740
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,464 | - |
$3,464
40,152
kWh
|
- | |
03 | 2.2511: Insulate bare equipment | $3,690 | $1,068 |
$3,690
42,790
kWh
|
- | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,176 | $2,500 |
$7,176
-
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,805 | $107 |
$1,911
22,274
kWh
|
$(-106.0) | |
06 | 2.4312: Improve lubrication practices | $5,365 | $800 |
$5,365
62,427
kWh
|
- | |
07 | 2.4133: Use most efficient type of electric motors | $2,587 | $1,528 |
$2,587
30,188
kWh
|
- | |
08 | 2.6218: Turn off equipment when not in use | $2,120 | - |
$2,120
24,619
kWh
|
- | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $834 | $2,250 |
$834
9,672
kWh
|
- | |
TOTAL RECOMMENDED | $29,077 | $8,253 |
$29,183
255,862
kWh
|
$(-106.0) | ||
TOTAL IMPLEMENTED | $11,267 | $4,846 |
$11,267
131,009
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs