Assessment Year | 1992 |
---|---|
Principal Product | PLASTIC,STEEL STRAPPING |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 144 |
Plant Area |
n/a
|
Annual Production | 72,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,352,420 | 21,774,033 |
kWh
|
$0.062 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $277,555 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4312: Improve lubrication practices | $4,940 | $2,000 |
$4,940
79,719
kWh
|
- | - | |
02 | 2.3312: Install efficient rectifiers | $100,936 | $125,000 |
$100,936
1,627,491
kWh
|
- | - | |
03 | 3.4115: Recover and reuse cooling water | $14,788 | $2,700 | - | - | $14,788 | |
04 | 2.8114: Change rate schedules or other changes in utility service | $25,123 | $44,000 | - |
$25,123
-
MMBtu
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $517 | $30 |
$517
8,206
kWh
|
- | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,376 | $500 | - |
$2,376
-
MMBtu
|
- | |
07 | 2.3212: Optimize plant power factor | $5,770 | - |
$5,770
93,200
kWh
|
- | - | |
08 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $123,105 | $327,000 |
$270,816
4,368,113
kWh
|
$(-107,711.0)
-
MMBtu
|
$(-40,000.0) | |
TOTAL RECOMMENDED | $277,555 | $501,230 |
$382,979
6,176,729
kWh
|
$(-80,212.0)
-
MMBtu
|
$(-25,212.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs