ITAC Assessment: OK0316
ITAC logo
ITAC Assessment: OK0316
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product AEROSTRUCTURES
NAICS
n/a
SIC 3721: Aircraft
Sales Range $10
M
to 50
M
# of Employees 270
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 5,100
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $201,526 5,516,999
kWh
Natural Gas $28,442 10,571
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,965 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,493

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $4,472 $5,500 $4,472
-
kWh
-
02 2.4239: Eliminate or reduce compressed air usage $458 $810 $458
19,050
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,023 - $1,023
32,532
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,012 - $2,312
95,838
kWh
$(-300.0)
TOTAL RECOMMENDED $7,965 $6,310 $8,265
147,420
kWh
$(-300.0)
TOTAL IMPLEMENTED $3,493 $810 $3,793
147,420
kWh
$(-300.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs