| Assessment Year | 1997 |
|---|---|
| Principal Product | Commercial Towers |
| NAICS |
n/a
|
| SIC | 3446: Architectural and Ornamental Metal Work |
| Sales Range | $50 M to 100M |
| # of Employees | 350 |
| Plant Area |
333,000
ft2
|
| Annual Production | 7,500
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $105,580 | 4,264,361 |
kWh
|
$0.025 |
| Electricity Demand | $222,707 | 12,388 |
kW-mo/yr
|
$17.98 |
| Electricity Fees | $(-1,488.0) | - |
|
- |
| Natural Gas | $344,882 | 103,157 |
MMBtu
|
$3.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $83,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,759 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $9,330 | $1,500 | - | - | $9,330 | - | - | - | - | - | - | |
| 02 | 2.2441: Preheat boiler makeup water with waste process heat | $5,780 | $8,410 | - | - | - |
$5,780
-
MMBtu
|
- | - | - | - | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $977 | $2,160 |
$666
26,964
kWh
|
$311
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $782 | $945 |
$483
19,637
kWh
|
$299
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
| 05 | 2.7135: Install occupancy sensors | $720 | $975 |
$468
18,757
kWh
|
$252
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
| 06 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $35,050 | $14,000 | - | - | - | - |
$1,225
-
gal
|
- | $33,592 | $233 | - | |
| 07 | 3.4151: Minimize water usage | $1,246 | $2,325 | - | - | - | - | - | - | - | - |
$1,246
-
Tgal
|
|
| 08 | 4.423: Move product using mechanical means | $30,000 | $24,000 | - | - | - | - | - | $30,000 | - | - | - | |
| TOTAL RECOMMENDED | $83,885 | $54,315 |
$1,617
65,358
kWh
|
$862
-
kW-mo/yr
|
$9,330 |
$5,780
-
MMBtu
|
$1,225
-
gal
|
$30,000 | $33,592 | $233 |
$1,246
-
Tgal
|
||
| TOTAL IMPLEMENTED | $1,759 | $3,105 |
$1,149
46,601
kWh
|
$610
-
kW-mo/yr
|
- | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs