Assessment Year | 1992 |
---|---|
Principal Product | DIE CAST MOLDS |
NAICS |
n/a
|
SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
n/a
|
Annual Production | 7,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $250,612 | 2,654,455 |
kWh
|
$0.094 |
Natural Gas | $18,053 | 2,690 |
MMBtu
|
$6.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,125 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,214 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,359 | $5,963 |
$4,342
46,014
kWh
|
- | $(-983.0) | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $650 | $500 | - |
$650
-
MMBtu
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $1,855 | $930 | - |
$1,855
-
MMBtu
|
- | |
04 | 2.7494: Install storm windows and doors | $508 | $1,100 | - |
$508
-
MMBtu
|
- | |
05 | 2.3191: Use demand controller or load shedder | $6,177 | $2,500 |
$6,177
-
kWh
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $4,275 | $2,098 |
$4,275
45,428
kWh
|
- | - | |
07 | 2.4312: Improve lubrication practices | $10,595 | $800 |
$10,595
112,837
kWh
|
- | - | |
08 | 2.8114: Change rate schedules or other changes in utility service | $3,706 | $4,000 |
$3,706
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $31,125 | $17,891 |
$29,095
204,279
kWh
|
$3,013
-
MMBtu
|
$(-983.0) | ||
TOTAL IMPLEMENTED | $5,214 | $6,893 |
$4,342
46,014
kWh
|
$1,855
-
MMBtu
|
$(-983.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs