| Assessment Year | 1990 |
|---|---|
| Principal Product | DROP HARDWARE |
| NAICS |
n/a
|
| SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 133 |
| Plant Area |
n/a
|
| Annual Production | 37,500,500
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $135,996 | 1,526,964 |
kWh
|
$0.089 |
| Natural Gas | $25,672 | 4,201 |
MMBtu
|
$6.11 |
| Fuel Oil #2 | $23,991 | 5,180 |
MMBtu
|
$4.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,698 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,603 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,615 | $7,500 |
$4,615
51,876
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,773 | $331 |
$2,773
31,067
kWh
|
- | - | |
| 03 | 2.6218: Turn off equipment when not in use | $2,110 | - |
$2,110
23,740
kWh
|
- | - | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $686 | $600 |
$686
7,620
kWh
|
- | - | |
| 05 | 2.2511: Insulate bare equipment | $493 | $200 | - |
$493
-
MMBtu
|
- | |
| 06 | 2.2511: Insulate bare equipment | $2,068 | $500 | - |
$2,068
-
MMBtu
|
- | |
| 07 | 2.1332: Convert combustion equipment to burn natural gas | $3,953 | $45,000 | - |
$(-28,743.0)
-
MMBtu
|
$32,696
-
MMBtu
|
|
| TOTAL RECOMMENDED | $16,698 | $54,131 |
$10,184
114,303
kWh
|
$(-26,182.0)
-
MMBtu
|
$32,696
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,603 | $200 |
$2,110
23,740
kWh
|
$493
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs