Assessment Year | 1990 |
---|---|
Principal Product | METAL LAMINATES |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 24 |
Plant Area |
n/a
|
Annual Production | 200,000
lb
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $58,240 | 528,136 |
kWh
|
$0.11 |
Natural Gas | $17,453 | 3,377 |
MMBtu
|
$5.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,821 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,943 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $261 | $34 |
$261
2,345
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,505 | $500 |
$1,505
13,775
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,267 | $214 |
$1,267
11,430
kWh
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $332 | - |
$332
2,931
kWh
|
- | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $546 | $1,080 |
$(-113.0)
(-1,172)
kWh
|
$659
-
MMBtu
|
|
06 | 2.2515: Use optimum thickness insulation | $9,910 | $80,000 |
$9,910
89,977
kWh
|
- | |
TOTAL RECOMMENDED | $13,821 | $81,828 |
$13,162
119,286
kWh
|
$659
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,943 | $80,748 |
$12,943
117,527
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs