| Assessment Year | 1989 |
|---|---|
| Principal Product | TEFLON & PVC COATED WIRE |
| NAICS |
n/a
|
| SIC | 3357: Drawing and Insulating of Nonferrous Wire |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
n/a
|
| Annual Production | 24,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $256,322 | 3,558,031 |
kWh
|
$0.072 |
| Natural Gas | $38,910 | 8,032 |
MMBtu
|
$4.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,978 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,476 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,402 | $441 |
$3,402
47,186
kWh
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,029 | - |
$1,029
14,361
kWh
|
|
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,097 | $9,000 |
$1,097
15,240
kWh
|
|
| 04 | 2.4312: Improve lubrication practices | $557 | $400 |
$557
7,620
kWh
|
|
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,670 | $594 |
$1,670
23,154
kWh
|
|
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,506 | - |
$1,506
20,809
kWh
|
|
| 07 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,869 | - |
$1,869
26,084
kWh
|
|
| 08 | 2.6212: Turn off equipment during breaks, reduce operating time | $16,848 | - |
$16,848
233,880
kWh
|
|
| TOTAL RECOMMENDED | $27,978 | $10,435 |
$27,978
388,334
kWh
|
||
| TOTAL IMPLEMENTED | $9,476 | $1,035 |
$9,476
131,594
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs