Assessment Year | 1988 |
---|---|
Principal Product | CONCRETE PIPES |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $5 M to 10M |
# of Employees | 55 |
Plant Area |
n/a
|
Annual Production | 78,000
ton
|
Production Hrs. Annual | 3,162
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $89,908 | 834,994 |
kWh
|
$0.11 |
Natural Gas | $5,527 | 925 |
MMBtu
|
$5.98 |
Fuel Oil #2 | $18,179 | 3,905 |
MMBtu
|
$4.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,608 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,013 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|
01 | 2.4312: Improve lubrication practices | $1,840 | $800 |
$1,840
18,464
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,908 | - |
$2,908
26,964
kWh
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $1,286 | $390 | - |
$1,286
-
MMBtu
|
|
04 | 2.7243: Improve air circulation with destratification fans / other methods | $3,369 | $3,400 |
$(-267.0)
(-2,345)
kWh
|
$3,636
-
MMBtu
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,386 | - |
$2,386
21,981
kWh
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $456 | - |
$456
4,103
kWh
|
- | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $363 | $500 | - |
$363
-
MMBtu
|
|
TOTAL RECOMMENDED | $12,608 | $5,090 |
$7,323
69,167
kWh
|
$5,285
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,013 | $890 |
$3,364
31,067
kWh
|
$1,649
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs