| Assessment Year | 1988 |
|---|---|
| Principal Product | FIBERGLASS TANKS |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 46 |
| Plant Area |
n/a
|
| Annual Production | 500
pieces
|
| Production Hrs. Annual | 3,276
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $77,605 | 678,781 |
kWh
|
$0.11 |
| Natural Gas | $27,299 | 5,570 |
MMBtu
|
$4.90 |
| Fuel Oil #2 | $26,208 | 4,586 |
MMBtu
|
$5.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,127 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,611 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7229: Air condition only space necessary | $2,449 | $4,244 |
$2,449
22,274
kWh
|
- | - | |
| 02 | 2.7492: Use proper thickness of insulation on building envelope | $3,900 | $26,730 | - |
$3,900
-
MMBtu
|
- | |
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $2,637 | $2,780 |
$275
2,638
kWh
|
$2,362
-
MMBtu
|
- | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $2,523 | $2,268 |
$(-456.0)
(-4,103)
kWh
|
$2,979
-
MMBtu
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,611 | - |
$1,611
14,654
kWh
|
- | - | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,145 | $2,600 | - | - |
$3,145
-
MMBtu
|
|
| 07 | 2.4322: Use or replace with energy efficient substitutes | $9,862 | $4,000 |
$9,862
89,683
kWh
|
- | - | |
| TOTAL RECOMMENDED | $26,127 | $42,622 |
$13,741
125,146
kWh
|
$9,241
-
MMBtu
|
$3,145
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,611 | - |
$1,611
14,654
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs