ITAC Assessment: ORC011
ITAC logo
ITAC Assessment: ORC011
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Education
NAICS 611210: Junior Colleges
SIC 8222: Junior Colleges and Technical Institutes
Sales Range less than $500
k
# of Employees 30
Plant Area 60,328
ft2
Annual Production 100
pieces
Production Hrs. Annual 3,380
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,314 1,221,900
kWh
Electricity Demand $168 25
kW-mo/yr
Natural Gas $32,740 5,037
MMBtu
TOTAL YEARLY COSTS $106,222
RECOMMENDED SAVINGS* $11,058 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,565 $11,700 $3,451
57,514
kWh
$114
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $494 $2,500 $494
8,237
kWh
- -
03 2.7225: Close outdoor air dampers during warm-up / cool-down periods $6,882 - $446
7,432
kWh
- $6,436
-
MMBtu
04 2.7447: Install vinyl strip / high speed / air curtain doors $117 $500 - - $117
-
MMBtu
TOTAL RECOMMENDED $11,058 $14,700 $4,391
73,183
kWh
$114
-
kW-mo/yr
$6,553
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs