Assessment Year | 2023 |
---|---|
Principal Product | Support Services |
NAICS | 611210: Junior Colleges |
SIC | 8222: Junior Colleges and Technical Institutes |
Sales Range | less than $500 k |
# of Employees | 30 |
Plant Area |
44,240
ft2
|
Annual Production | 100
pieces
|
Production Hrs. Annual | 3,380
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $45,843 | 763,440 |
kWh
|
$0.060 |
Electricity Demand | $14,557 | 1,878 |
kW-mo/yr
|
$7.75 |
Electricity Fees | $8,405 | - |
|
- |
Natural Gas | $31,394 | 4,034 |
MMBtu
|
$7.78 |
TOTAL YEARLY COSTS | $100,199 | |||
RECOMMENDED SAVINGS* | $31,760 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,690 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,713 | $12,000 |
$1,650
27,479
kWh
|
$63
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $1,211 | $2,500 |
$1,211
20,163
kWh
|
- | - | |
03 | 2.1224: Replace boiler | $3,391 | $30,000 | - | - |
$3,391
-
MMBtu
|
|
04 | 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation | $8,755 | $1,000 |
$4,720
78,609
kWh
|
- |
$4,035
-
MMBtu
|
|
05 | 2.2437: Recover waste heat from equipment | $16,690 | - |
$643
10,704
kWh
|
- |
$16,047
-
MMBtu
|
|
TOTAL RECOMMENDED | $31,760 | $45,500 |
$8,224
136,955
kWh
|
$63
-
kW-mo/yr
|
$23,473
-
MMBtu
|
||
TOTAL IMPLEMENTED | $16,690 | - |
$643
10,704
kWh
|
- |
$16,047
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs