ITAC Assessment: ORC008
ITAC logo
ITAC Assessment: ORC008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Provide public services
NAICS 921140: Executive and Legislative Offices, Combined
SIC 8111: Legal Services
Sales Range less than $500
k
# of Employees 94
Plant Area 81,308
ft2
Annual Production 10,000
units
Production Hrs. Annual 2,808
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,505 378,899
kWh
Electricity Demand $19,132 2,189
kW-mo/yr
Electricity Fees $7,135 -
Natural Gas $16,476 1,476
MMBtu
TOTAL YEARLY COSTS $65,248
RECOMMENDED SAVINGS* $8,078 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7132: Install timers on light switches in little used areas $2,876 $500 $2,876
47,936
kWh
- -
02 2.7135: Install occupancy sensors $474 $100 $474
7,987
kWh
- -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $959 $1,500 $959
16,150
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,527 $4,000 $478
8,050
kWh
- $1,049
-
MMBtu
05 2.7234: Use heat pump for space conditioning $668 $5,000 $419
7,060
kWh
$249
-
kW-mo/yr
-
06 2.6231: Utilize controls to operate equipment only when needed $1,574 $500 - - $1,574
-
MMBtu
TOTAL RECOMMENDED $8,078 $11,600 $5,206
87,183
kWh
$249
-
kW-mo/yr
$2,623
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs