Assessment Year | 2022 |
---|---|
Principal Product | Heaters and Controls |
NAICS | 333414: Heating Equipment (except Warm Air Furnaces) Manufacturing |
SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
Sales Range | $50 M to 100M |
# of Employees | 95 |
Plant Area |
141,000
ft2
|
Annual Production | 3,600
pieces
|
Production Hrs. Annual | 4,125
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $126,191 | 2,233,200 |
kWh
|
$0.057 |
Electricity Demand | $114,688 | 6,009 |
kW-mo/yr
|
$19.09 |
Electricity Fees | $5,680 | - |
|
- |
Natural Gas | $44,314 | 3,445 |
MMBtu
|
$12.86 |
TOTAL YEARLY COSTS | $290,873 | |||
RECOMMENDED SAVINGS* | $38,947 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $15,235 | $8,435 |
$1,985
35,138
kWh
|
- | - |
$13,250
-
MMBtu
|
- | |
02 | 4.212: Adopt in-house material generation | $11,462 | $31,920 |
$(-425.0)
(-7,522)
kWh
|
- | - | - | $11,887 | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,904 | $3,000 |
$2,904
51,402
kWh
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,769 | $2,815 |
$2,769
49,003
kWh
|
- | - | - | - | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $2,371 | $4,045 |
$1,203
21,285
kWh
|
$1,168
-
kW-mo/yr
|
- | - | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $2,278 | $500 | - | - | $2,278 | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,116 | $2,790 |
$562
9,950
kWh
|
$554
-
kW-mo/yr
|
- | - | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $812 | $1,090 |
$592
10,477
kWh
|
$220
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $38,947 | $54,595 |
$9,590
169,732
kWh
|
$1,942
-
kW-mo/yr
|
$2,278 |
$13,250
-
MMBtu
|
$11,887 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs