Assessment Year | 2024 |
---|---|
Principal Product | cheese, whey powder, ice cream |
NAICS | 311513: Cheese Manufacturing |
SIC | 2022: Natural, Processed, and Imitation Cheese |
Sales Range | $100 M to 500M |
# of Employees | 563 |
Plant Area |
333,974
ft2
|
Annual Production | 110,900,000
units
|
Production Hrs. Annual | 8,712
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,825,952 | 56,959,306 |
kWh
|
$0.050 |
Electricity Demand | $435,939 | 86,586 |
kW-mo/yr
|
$5.03 |
Electricity Fees | $27,721 | - |
|
- |
LPG | $1,405,407 | 107,578 |
MMBtu
|
$13.06 |
Other Energy | $707,781 | 24,979 |
MMBtu
|
$28.34 |
TOTAL YEARLY COSTS | $5,402,800 | |||
RECOMMENDED SAVINGS* | $99,611 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|
01 | 2.8223: Add air shields to trucks to increase fuel mileage | $79,249 | $259,200 | - | - |
$79,249
-
MMBtu
|
|
02 | 2.2511: Insulate bare equipment | $6,565 | $7,289 |
$6,565
143,332
kWh
|
- | - | |
03 | 2.2211: Use optimum temperature | $6,284 | - |
$6,284
137,202
kWh
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,111 | - |
$2,637
53,151
kWh
|
$474
-
kW-mo/yr
|
- | |
05 | 2.4322: Use or replace with energy efficient substitutes | $2,591 | $3,426 |
$2,232
46,021
kWh
|
$359
-
kW-mo/yr
|
- | |
06 | 2.2511: Insulate bare equipment | $1,811 | $4,166 |
$1,811
39,547
kWh
|
- | - | |
TOTAL RECOMMENDED | $99,611 | $274,081 |
$19,529
419,253
kWh
|
$833
-
kW-mo/yr
|
$79,249
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs