ITAC Assessment: OR0796
ITAC logo
ITAC Assessment: OR0796
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Cases of cans and bottles of soft drinks.
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 132
Plant Area 283,000
ft2
Annual Production 23,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $379,730 6,498,912
kWh
Electricity Demand $109,952 13,993
kW-mo/yr
Electricity Fees $50,547 -
Natural Gas $195,332 33,064
MMBtu
TOTAL YEARLY COSTS $735,561
RECOMMENDED SAVINGS* $218,789 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.2136: Install / repair insulation on steam lines $733 $546 - - $733
-
MMBtu
-
02 4.212: Adopt in-house material generation $86,946 $168,430 $(-6,611.7)
(-113,156)
kWh
$(-1,218.4)
-
kW-mo/yr
- $94,777
03 2.4222: Install adequate dryers on air lines to eliminate blowdown $584 $2,239 $540
9,243
kWh
$44
-
kW-mo/yr
- -
04 2.9114: Use solar heat to make electricty $130,526 $1,312,500 $108,125
1,850,527
kWh
$22,401
-
kW-mo/yr
- -
TOTAL RECOMMENDED $218,789 $1,483,715 $102,053
1,746,614
kWh
$21,227
-
kW-mo/yr
$733
-
MMBtu
$94,777
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs