| Assessment Year | 2024 |
|---|---|
| Principal Product | Recycled sorted metal |
| NAICS | 331491: Nonferrous Metal (except Copper and Aluminum) Rolling, Drawing, and Extruding |
| SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 54 |
| Plant Area |
117,000
ft2
|
| Annual Production | 18,000
ton
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $95,000 | 1,258,640 |
kWh
|
$0.075 | |
| Electricity Demand | $112,944 | 9,556 |
kW-mo/yr
|
$11.82 | |
| Electricity Fees | $31,217 | - |
|
- | |
| Natural Gas | $3,472 | 272 |
MMBtu
|
$12.76 | |
| Fuel Oil #1 | $4,278 | 126 |
MMBtu
|
$34.02 | |
| Waste Disposal Costs | |||||
| Water Usage | $946 | 105 |
Tgal
|
$9.01 | |
| Water Disposal | $1,748 | 106 |
Tgal
|
$16.46 | |
| TOTAL YEARLY COSTS | $249,605 | ||||
| RECOMMENDED SAVINGS* | $27,474 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $5,498 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,513 | - |
$4,513
59,792
kWh
|
- | - | - | |
| 02 | 2.3212: Optimize plant power factor | $1,616 | $14,338 | - | - | - | $1,616 | |
| 03 | 2.1321: Replace fossil fuel equipment with electrical equipment | $4,115 | $1,800 |
$(-163.0)
(-2,162)
kWh
|
- |
$4,278
-
MMBtu
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $985 | - |
$564
7,470
kWh
|
$421
-
kW-mo/yr
|
- | - | |
| 05 | 2.4225: Install common header on compressors | $16,245 | $4,904 |
$2,636
34,923
kWh
|
$13,609
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $27,474 | $21,042 |
$7,550
100,023
kWh
|
$14,030
-
kW-mo/yr
|
$4,278
-
MMBtu
|
$1,616 | ||
| TOTAL IMPLEMENTED | $5,498 | - |
$5,077
67,262
kWh
|
$421
-
kW-mo/yr
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs